4 min read

Tom Brennan, public affairs director with Western Maine Energy Storage, explains to Dixfield selectmen Monday night the Cianbro-affiliated company’s hopes to build a $1 billion hydropower storage project in Dixfield. From left, facing the camera, are Vice Chairman Peter Holman and Dan Carrier Sr. (Bruce Farrin/Staff Writer)

DIXFIELD — Representatives from a company developing a $1 billion pumped storage hydropower project in Oxford County met Aug. 11 with the Select Board.

“One thing to understand is that this is a long process … about four or five years” said Tom Brennan, public affairs director with Western Maine Energy Storage. “It’s going to be regulated by (the Federal Energy Regulatory Commission).”

The project would be the first of its kind in Maine and among the largest in the Northeast, capable of generating about 500 megawatts of on-demand power. The project would use two 100-acre artificial reservoirs to store and release water for electricity generation during peak demand.

According to the application to federal regulators, the developer estimates annual energy output at 1 million megawatt hours; for reference, Maine uses a little more than 11 million megawatt hours of electricity a year.

Western Maine Energy Storage was established in May 2024 and operating out of Cianbro Corp.’s Pittsfield headquarters. It submitted its application for a preliminary permit to federal regulators July 21.

Advertisement

Brennan was joined at the meeting by Lauren Walsh, Cianbro’s environmental manager, and Tom Saviello, a professional forester and former Maine state legislator.

Brennan said Walsh is guiding the permitting process. “There’s going to lots be of opportunity to come back and talk to you folks,” he said. “We’re right at the very beginning of this. The preliminary application was just submitted.”

The project is slated to be located off Ludden Lane, which is off the Canton Point Road, in a relatively undeveloped area.

Walsh noted it’s near the Central Maine Power transmission corridor, “one of the reasons for the selection of this site.”

Walsh said that as it stands, the whole project is sited in Dixfield, except for a small corner in Canton.

A conceptual rendering of the proposed pumped storage hydropower project in Dixfield and Canton shows the two artificial reservoirs and the penstock that would carry water between them. (Courtesy of Western Maine Energy Storage)

“The essence of this project really is to construct a water battery,” Brennan told the board Monday. “And the way it works is you have a water reservoir at a higher elevation than the second reservoir, which is at a lower elevation. … we have all these renewables that are functioning now, but the thing is, the sun doesn’t shine all the time and the wind doesn’t blow all the time.

Advertisement

“So when you have plentiful power and the rates are fairly cheap, you pump water up, and when it’s costly and the grid is strained, you let it flow back down through turbine and put that power to generate back into the grid and fill the gap.”

Brennan noted that this is not new technology. “It really started in Switzerland in the 1890s,” he said. “But there are about two dozen of the facilities around North America; none in Maine but there are two in western Massachusetts. So they’ve been time tested.”

Walsh said each reservoir is roughly 100 acres. “The entire project footprint that we’re proposing is roughly 625 to 630 acres.”

Asked who will own the station once complete, Walsh said Cianbro is developing it. “It’s a big project, so we don’t expect we’ll be the only owner. There will be investors.”

Board member Laurie Woodhead asked, “Who gets the benefit from this? Where does this go?”

Brennan responded, “It will go into the grid and it will stabilize the flow of electricity basically, and the resilience of the grid.

“A couple of winters ago, we had a bunch of storms and our power supply was impacted. A facility like this would be able to level things off and pick up the slack. I think it benefits everybody.”

Walsh said they’re early in the permitting phase, so the preliminary permitting application generally outlines the location for the project, and through FERC process, “we will go through several studies benefits the environmental impact, finalizing the location for those reservoirs. That permitting process will take anywhere from three to five years.”

Brennan noted, “We’d love to pursue constructing one of these facilities here in western Maine.”

Bruce Farrin is editor for the Rumford Falls Times, serving the River Valley with the community newspaper since moving to Rumford in 1986. In his early days, before computers, he was responsible for...

Join the Conversation

Please sign into your CentralMaine.com account to participate in conversations below. If you do not have an account, you can register or subscribe. Questions? Please see our FAQs.